Dr. Lu

Technical Director
MaleNationality
Share

Work experience

  • Technical Director

    Kona Energy UK
    2024.06-Current(2 years)
    (1 year 6 months) Developing and delivering the GW BESS project through U.K. and U.S. ERCOT market and meet NetZero target. Engaging with various stakeholders to ensure that the project can be successfully implemented with optimal cost. Working with TSO for the grid connection process to accelerate the BESS project connection. Working with various OEM including BESS, PCS, transformer suppliers, EPC/ BOP, Integrator with providing technical specification and requirements. Managing BESS and BOP RFP/RFQ and procurement process. Technical support for project completion and FID.
  • Technical Director

    Hithium Energy Storage
    2023.03-2024.06(a year)
    (1 year 4 months) 1. Provide technical solution for LFP battery energy storage system for European Market customer. 2. Review and optimize the battery system design and proposal for various projects. 3. Engage with renewable industry stakeholders (developer, integrator, owner) from different sectors and provide techno-commercial solution for battery storage products. 4. Attend conference to understand the industrial needs for next generation battery storage technology such as sodium battery and feedback to Hithium R&D team. 5. Lead Hithium BESS engineering project team. 6. Develop new BESS product within the team and compliance with industrial safety standards such as UL9540A, IEC62619, UL1973, NFPA855 etc. 7. Work with various PCS suppliers (such as SMA, Delta, PE, Ingeteam) and EMS suppliers for the BESS project. 8. Providing technical support for BESS project commissioning for European customers.
  • Principal Consultant

    Enzen Global Limited - UK
    2022.03-2023.09(2 years)
    (1 year 7 months) 1. Various voltage level DNO generation and demand connection analysis and Point of Connection identification. 2. Provide renewable connection (including PV, battery storage etc) technical support to various electricity industry partner. 3. Liaising with stakeholders from various department including Ofgem, utility company to achieve U.K. Netzero 2050 strategic target.
  • Infrastructure Planning Engineer

    UK Power Networks
    2021.02-2022.03(a year)
    (1 year 2 months) Developing the Extra High Voltage (EHV) and 132kV, HV,LV electricity network in UK Power Networks regulated EPN area in a coordinated and economic manner to satisfy the Distribution and Grid Codes obligations and requirements. • Design and operation of UK distribution systems at various voltage levels, including distributed generation (DG) and energy storage; • Apply the principles of electricity network assets such as transformers, switchgear, cables, overhead lines, protection, substation design and others; • Build the electricity network modelling techniques including the importance of power flow, fault levels and voltage profile management in PowerFacotry; • Design the lifecycle of projects from concept to completion; • Compliance Distribution/Grid Code and National Grid Connection and Use of System Code (CUSC); • Design the system following the requirements of Engineering Recommendations, including P2, G98, G99, G74, G75, G77, G5, P28, P29; • Carry out feasibility studies/assessments for the connection of Distributed Energy Resources (DER) such as wind farms, solar photovoltaic and energy storage; • Carry out assessment for high demand customer connections such as data centres, industrial or commercial developments; • Apply Construction Design and Management (CDM) Regulations.
  • Senior Engineering Consultant

    Atkins
    2020.03-2021.01(a year)
    overseeing power system advisory, electricity transmission and distribution activities.
  • Power System Engineer (DNO and Demand Sector)

    National Grid
    2019.01-2020.03(a year)
    5 years 1 month (1 year 3 months) Demand and Distribution Network system design
  • Authorised Power System Engineer

    DNO
    2015.03-2020.03(5 years)
    (5 years 1 month) Power System Engineer with National Grid authorization National Grid Network System analysis including Thermal, Voltage, Fault level, Stability and Negative Phase sequence analysis and modeling. Renewable and Battery generations at NGET Grid code/SQSS/CUSC code transmission system code analysis and design Commercial offer document including generation and demand Load and non load related scheme OFGEM RIIO industry market and framework Stakeholder engagement Commercial and customer focus Nationalgird business procedure

Projects

  • Development of transformer and Fault Current Limiter for High Power dc networks (funded by epsrc grant)

Educational experience

  • Institute of Asset Management

    Asset Management
    2017.01-2017.01
  • University of Aberdeen

    Electrical and power systems
    2010.02-2014.02(4 years)
  • 英国谢菲尔德大学

    MPhil, Automatic Control and System engineering
    2008.11-2009.12(a year)
  • Harbin Institute of Technology

    control engineering
    2006.01-2008.01(2 years)
  • Harbin Institute of Technology

    Control engineering
    2002.01-2006.01(4 years)

Certificates

Chartered Engineer
Resume Search
Nationality
Job category
City or country
Jobs
Candidates
Blog
Me